Stages of construction project and consultants involved Q1

Q.
a) Explain the development stages of a construction project. (13 marks)

b) Explain the term 'consultants' in a construction project and elaborate their roles in the development process. (12 marks)

(25 marks, 2017 Q1)

A.
a) Development stages of a construction project

Similar question was asked in

2011 Q1
2014 Q1
Briefing stage
Designing stage
Tendering stage
Constructing stage


b) 'consultants'

Similar question was asked in
2011 Q1
2016 Q8 D07 LEc

Consultants directly involved in each stage are:

I) Briefing Stage - Architect
II) Designing Stage - Architect & Structural Engineer
III) Tendering Stage - Architect & Quantity Surveyer
IV) Construction Stage - Architect & Various Engineers, Project Manager/Engineer, CDM Coordinator*.

* CDM - Construction (Design and Management) is a requirement by CDM Regulation 2007 in the UK. In Malaysia, there is no CDM Regulation (**) it is occupational Safety and Health Act, 1994 (OSHA 1994). The officer is DOSH certified, Department of Occupational Safety and Health, Ministry of Human Resource (Kementerian Sumber Manusia).

** Hassan, Fadzil and Ahmad Rashid , Zul Zakiyuddin and Adnan, Hamimah. 2010. A study on Malaysian legal framework and risk management. Journal of Politics and Law. Vol 1, No.2. Page 26-32